![]() ![]() In the Detail Gantt view, total slack appears as a thin teal line. Total slack (or float) is the amount of time this sequence of tasks can slip before it affects the finish date of the project. In the Detail Gantt view, noncritical tasks appear in blue. The lower sequence of tasks does not drive the finish date of the project, and therefore the tasks are not critical. In the Detail Gantt view, critical tasks appear in red. All tasks in this sequence are on the critical path and are called critical tasks. ![]() ![]() ![]() The top sequence of tasks has no slack (also called "float"), and therefore drives the finish date of the project. How does Project calculate the critical path?Ĭan I see the critical path across multiple projects?īy knowing and tracking the critical path for your project, as well as the resources assigned to critical tasks, you can determine which tasks can affect your project's finish date and whether your project will finish on time. What does the critical path show about your project? If one task on the critical path moves, the end date of the project will move as well. Starting dates can be assigned to each activity by doing a forward pass proceeding from left to right in the network diagram beginning with the project start date.You may wonder, "What ultimately determines the length of my project?" The answer is the critical path, which is the series of tasks that dictates the finish date of the project. The dates derived by this method are the early start (ES) dates. The early start date for an activity is the earliest date the activity can begin. The estimate considers durations and resource availability calendars. Assign the calculated date as the early start date of the successor activity.Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and add the number of off-days that the activity would span on those calendars.Add the lag time or subtract the lead time.Īdd the predecessor activity’s duration to its start date.įollow these steps to calculate the early start dates of subsequent activities, assuming finish-start relationships: To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have no predecessor activities. The next step is to work through the network diagram from right to left beginning with the mandated completion date, which is a milestone that is set in the project plan. Subtract the duration of each activity in each path to determine the latest date the activity could begin and still meet the project completion date. Resource calendars must be considered in the backward pass as well as the forward pass. Assign the calculated date as the late start date of the predecessor activity.Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and subtract the number of off days that the activity would span on those calendars.Subtract the lag time or add the lead time to the late finish date.Subtract the predecessor activity’s duration from its late finish date.Follow these steps to calculate the late start dates of predecessor activities, assuming finish-start relationships: To calculate late start dates, begin with the project completion milestone and assign that date as the finish date of its predecessor activities. The difference between the early start date and the late start date for activities on the critical path is usually the same as the total float, unless the activities are affected by the resource calendars differently in the forward and backward pass. What is the difference between free float and project float?.If the last activity in the critical path has a completion date that is five days later than the project completion date, the project has a _ _ (two words) of five days.If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _ time.The difference between the sum of the activity durations along the critical path and the project completion date is the project _.The path through the network diagram that has the longest total duration is the _ path.For example, if a piece of key equipment is only available for a few days, activities that depend on it have the same start and finish dates in the forward and backward passes. ![]()
0 Comments
Leave a Reply. |